Activity 10 B: Network Diagram
Learning Goal: I’m working on a management writing question and need an explanation and answer to help me learn.
Using the following information:
- Build a network diagram
- Identify the early start, early finish, late start late finish for each activity
- Identify the critical path
- Identify the duration of the critical path
- What is the float of Activity B
- What is the float of Activity H
Activity | Predecessor | Duration in Days |
A | Start | 3 |
B | Start | 6 |
c | A, B | 12 |
D | B | 5 |
E | D | 4 |
F | C | 6 |
G | E,F | 8 |
H | E | 7 |
I | H | 3 |